To Build or Not to Build ...
|
(These Q&A's were published in the RIIA Newsletter in March of 2010)
Rising
maintenance costs, engineering expenses, insurance fees, and repairs needed to
keep our bridge safe reveal that no matter
which Bridge Management Option is chosen,
current RIIA Membership Dues are
not keeping up with actual and projected costs for continued maintenance of
the existing bridge.
Additionally,
construction costs are higher than 1996's projections, banks are not making
20/30-year loans for bridges, and state
agencies are enforcing even stricter environmental regulations. Projected higher costs needed to maintain the
bridge drove the decision
to investigate other bridge alternatives and funding options. In October of this year, a re- activated Bridge
Committee (BC) comprised of new and old volunteers have reviewed reports and
information in the 2005, 2007, 2008 2009 Exeltech & Sargent Engineering
Reports and the 2009 Hirko Report. The BC unanimously agreed with 3 options as
the most viable bridge management solutions. They are:
- RID -- petition Pierce County
to construct a new bridge as a Road Improvement
District (RID)
- REPAIR -- continue maintaining the bridge
- RECONSTRUCT -- RIIA contracts with an engineering
firm to build a new bridge or
replace the bridge in phases
Each
alternative is being researched and discussed for feasibility and cost. Over the next
couple of months, a preliminary
report will be developed to provide to the Board and the membership at our
Annual Meeting onMay 17, 2010. In the
meantime, and because interim
bridge repairs must continue, an updated
Maintenance Plan by the engineer is underway
and will be available for May's
meeting.
The Q&A's that follow provide
detailed information on the challenges we face regarding our
bridge. Please take the time to read them so that you
can be an informed participant
during bridge discussions at our May
meeting. If you have additional
questions or would
like to attend a BC meeting, please call the Island Manager at 265-8489 for more
information.
|
What You Might Like to Know ...
|
BRIDGE
HISTORY
- 1958 -- Matthew constructs 2-Lane
788-ft x 20-ft Timber Bridge
with Concrete Decking
- 1977 -- RIIA purchases the Bridge and Access Road (off
Kopachuck) for $50,0000
- 1995 -- Engineerls Inspection reveals
on-going deterioration with remaining bridge life of approx 20 years (to 2016)
**
- 1996 -- Membership approves Annual Special
Assessment called the Bridge Replacement Fund (BRF)
- 1996 -- Each lot assessed $130 BRF with
8.04% added each year thereafter (BRF will be $610 in 2016)
- 2005 -- Updated construction estimates
reveal BRF falling behind projected bridge replacement construction costs. Board
initiates full review of bridge conditions and options.
- 2007 -- Board approves contract to study
Bridge Options -- Hirko Report
- 2009 -- Volunteer Bridge
Committee formed to review Bridge Options
(** per
engineerls report in 1995, 2016 represents the year when major upgrades may be
required)
|
Questions and Answers ...
|
1. QUESTION -- How much are we spending on Bridge Repairs? Over the last 8 years, RIIA spent a total of $434,118 on bridge repairs only. That’s an average of $54,265 per year or $271 annually per lot (based on 200 lots).
2. QUESTION -- How much of our Dues goes to MAINTAIN the bridge? Originally, 23% of your monthly dues were earmarked for the Bridge Maintenance Fund (BMF). But in 2008, the membership voted to combine the BMF together with RIIA’s other operating funds (roads, capital and general) -- Currently dues go into one fund with no special designation. Over the past five years the cost of bridge inspections, insurance, taxes and repairs have exceeded 50% of the total dues amount billed to the membership each year.
3. QUESTION -- Is there another fund for the Bridge? Yes. In 1996, RIIA began collecting a special assessment for the bridge called the Bridge REPLACEMENT Fund (BRF). This was a special bylaw amendment establishing a fund specifically earmarked for bridge replacement. There is approximately $800,000 in the BRF (it fluctuates with the market). Last year each lot paid $355. Per the bylaws, this amount increases by 8.04 percent per year until 2016 when this payment schedule sunsets.
4. QUESTION -- What happens after 2016? The annual BRF collection will expire. RIIA must initiate a bylaw amendment in order to continue collecting these funds. An increased amount may need to be considered. This would require approval by two-thirds of RIIA’s eligible (current with dues) voting members.
5. QUESTION -- Why not use the Bridge REPLACEMENT funds (BRF) to maintain the bridge? Using this fund for general bridge maintenance would require a bylaw amendment approved by two-thirds of RIIA’s eligible voting members. Maintenance costs would eventually deplete the BRF entirely.
6. QUESTION -- Why can’t we just keep paying current dues and leave the bridge issue alone? Unfortunately, engineering studies have identified some very costly maintenance upgrades within the next five to ten years. Current RIIA Membership Dues are not keeping up with those costs for continued maintenance of the existing structure. No matter which option is chosen, a RIIA dues increase will be necessary in the future.7. QUESTION -- Why can’t we ask Pierce County to build a bridge? Our
bridge is privately owned by the membership and it is not built to
current county standards. By law, the County is not obligated to fund a
new bridge. The only way that the County would consider taking over our
bridge is if a majority of properties petition to become a Road
Improvement District (RID). Under this scenario, Raft Island owners
would fund the new bridge costs through property taxes.
8. QUESTION -- Can we become a Road Improvement District (RID)? Based on research over the last several years, we have learned the following: The
first step requires a “Special Benefits Study” (SBS) by Pierce County
to find out if the special benefit resulting from the construction of a
new bridge would be equal to or greater than the cost to each owner. The
governing law (RCW) states that “…no parcel can be assessed for more
than the special benefit received.” If RIIA votes to move forward with a
SBS, it will cost RIIA between $20,000 to $50,000 (approximately $100
to $250 per lot) and will take three to six months to complete. Once
completed the SBS will provide an itemized list of property owners and
each lot’s proposed special assessment. If a majority (two thirds of
RIIA”s eligible voting members) approves of the “special assessment” and
petitions Pierce County to become an RID, the County Council will make
the decision whether to approve the application. If they approve, each
lot owner will be obligated to pay the special assessment amount in the
form of an annual fee added to their property tax for 20 years.
9. QUESTION -- How much would my property be assessed? Until
the “Special Benefits Study” (SBS) is completed, it’s impossible to
know exactly how much each property owner would have to pay each year
because the fee is determined parcel by parcel. Based on a estimated
construction cost of $7.8 million and 200 lots, the average lot owner
could be assessed nearly $40,000 or up to $2,000 each year for 20 years.
(This does notinclude debt service estimated at today’s rate of 4% .)
10. QUESTION -- If Pierce County Council accepts our RID petition, what are the benefits? A
county-owned bridge means that the membership would no longer have to
insure, inspect or fund future repairs of the bridge. The County, rather
than RIIA, will be responsible for collecting related funds in the form
of property taxes.
11. QUESTION -- What would it cost to replace our bridge if the County builds it? Based on estimates from the County, $7.8M using an average of $275 per sq ft (bridge deck surface).
12. QUESTION -- Do we have enough land or “right-of-way” for Pierce County to construct a bridge? Pierce
County has road width regulations that may require additional land to
construct a new bridge. We would also be required to bring the access
road up to current county standards.
13. QUESTION -- What if we build our own bridge -- who would manage it and where would the money come from? This
work would be managed by a consultant (professional engineering firm)
hired by RIIA. Funding strategies would require future investigation.
The existing Bridge Replacement Fund (BRF) could be used to leverage
funds (borrowing at prevailing rates and terms).
14. QUESTION -- What would it cost to replace our bridge if RIIA builds it? Current
estimates suggest between $4M to $5M for a 24-ft wide bridge if RIIA
builds it. County construction standards require prevailing wage and
documentation that typically costs more and often takes longer. County
standards include standardized widths, sidewalk provisions and
additional features that we may not require. (Note: RIIA would construct
the structure to current truck weight standards for increased
capacities.)
15. QUESTION -- What will happen to the value of my home if we choose to finance a new bridge? All
bridge options have the potential of impacting the value of island
property. The Board, the Bridge Committee and the Bridge Replacement
Fund Committee are working to protect the value of everyone’s homes no
matter which option is ultimately selected by the membership.
16. QUESTION -- If the remaining life expectancy in 1995 was 20 yrs, does that mean our bridge will fail in 2016? This
projection was a 1995 estimate based on the judgment of a licensed
engineer. The engineer gave his best guess at what year those repairs
create a dollar for dollar diminishing return. However, our continued
maintenance can extend the life of the bridge. And it is conceivable
that we could continue maintaining the bridge indefinitely. The negative: The costs to stage each major repair, one fix at a time, makes the total cost of this approach very expensive. The positive: These fixes and costs could be spread over a longer period of time with the debt shared by current and future residents.
17. QUESTION -- What is the current condition of our bridge? Annual
engineering inspections continue to rate our bridge in Fair**
condition. The Federal Highway Systems has astandardized “condition
rating”. GOOD = A range from no problems to some minor deterioration of structural elements. **FAIR
= All primary structural elements are sound but may have deficiencies
such as minor section loss, deterioration, cracking, spalling, or scour. POOR
= Advanced deficiencies such as section loss, deterioration, cracking,
spalling, scour, or seriously affected primary structural components.
Bridges rated in poor condition may be posted with truck weight
restrictions.
18. QUESTION – Can the bridge be maintained indefinitely? Yes. It was constructed using modular elements. Bridges, new and old, are in a continuous state of decay.
19. QUESTION – Is maintaining our bridge indefinitely, cost effective? The 2005 Sargent Engineering Report stated, “replacement of the bridge in the next ten years makes the most economic sense.”
20. QUESTION -- If we build a new bridge ourselves, won’t we have to continue managing it? Yes.
Although the early years of a new bridge would require very few
repairs, RIIA must maintain a bridge fund for bridge insurance,
inspections, future repairs and (after 75 to 100 years) eventual
replacement.
21. QUESTION -- How do we know what kind of bridge to build? RIIA
will solicit requests from licensed engineers to assist in designing
the most cost effective and functional bridge to meet our needs. It is
likely that a new bridge would use concrete instead of timber piling.
22. QUESTION -- Can we build a causeway across the tideflats? The
short answer is no; Fish and Wildlife will not permit this option. The
Bridge Committee is looking at a conceptual design that uses a partial
fill at both ends to shorten the structural length of the bridge and
reduce costs but we have not met with any agencies for feedback. Once
the membership chooses a preferred bridge option, specific construction
details will be investigated by the engineers.
23. QUESTION -- Can our creosote pilings be replaced? Wood
piling treated with creosote are no longer easy to permit but other
types of treated wood are. Under “maintenance” allowances, we can
continue to replace failing piling members with other types of treated
wood (not creosote).
24. QUESTION -- What is the lifespan of concrete and steel? About 75 (plus or minus) years.
25. QUESTION -- What is better -- concrete or steel piling? Current
estimates suggest that concrete is cheaper and easier to permit --
steel piling are easier to drive but may not last as long due to rust
and corrosion.
26. QUESTION -- Will a new bridge allow bigger trucks to travel across our bridge? The
standard highway rating is H-22. Our bridge rating is lower (H15-44).
If we reconstruct the bridge, we will build to current standards. If the
County reconstructs our bridge (under the RID), it will be to current
county standards.
27. QUESTION -- What about permitting for the in-water work? State
and federal agencies permit in-water work when juvenile and adult fish
are not migrating through the area. These “fish windows” are determined
by the agency and prescribed as part of our permit approval.
28. QUESTION -- Can a new bridge be permitted? Yes.
There is no reason to believe that permitting with all county, state
and federal agencies will prohibit construction of a new bridge. The
application process and fees will be part of the overall bridge
construction project cost.
29. QUESTION -- Will the bridge be closed during construction? No. Any construction plan will require that one lane will be open throughout reconstruction of the bridge.
30. QUESTION -- How long will permitting and bridge construction take? The
permit process begins when a set of plans is submitted. The SEPA
checklist can take up to 45 days; Fish and Wildlife has 45 days after
that and a Shoreline permit can take 120 days or more. The Army Corps of
Engineers could be slow but that’s where pressure from our state and
county representatives can help. All applications can run concurrently.
In short, a safe estimate is up to 1 ½ years once plans are submitted.
In-water construction will be tied to an annual “fish window” cycle and is expected to take about a 12 to 18 months.
31. QUESTION -- Will we need a Washington State Department of Natural Resources (DNR) review? Our
regional representative from the Department of Natural Resources (DNR)
determined that no State owned aquatic lands are within our project area
footprint because the shallow passage between the island and mainland
is privately owned.
32. QUESTION -- Will we need a Historic Preservation Act review? A
cultural resource survey to assess the risk of disturbing archeological
artifacts is routine. As part of the SEPA permit process, the
Department of Archeology and Historic Preservation (DAHP) and other
agencies have an opportunity to comment on the likelihood of cultural
resources buried within the subject site area. Since it’s unlikely for
there to be a gravesite or historic native village within the tidelands,
our “risk” is very low and should not be an issue.
33. QUESTION -- If permitting takes over 1 year and construction within a fish window takes another year or so, what do we need to do now? If
there is a decision to reconstruct the bridge in phases, we would
solicit engineers to develop design options for the project. Before
proceeding we will have to identify the most equitable funding
strategies. This work will take up to a year to complete and will be
presented to the general membership. If there is a decision to take the
next step with Pierce County for a RID, the membership must vote to fund
the Special Benefits Study (SBS see Question #8 & #9). Either way
and in the short term, a conservative bridge maintenance/repair plan
will continue. Results from the updated Maintenance Plan is expected
before the annual meeting in May. It will tell us whether a dues
increase is necessary to keep up with repairs.
34. QUESTION -- Can we apply for grants to finance the bridge? Funding
for private construction projects is highly unlikely. Our best asset is
the Bridge Replacement Fund because it could be leveraged to finance
loans or other funding sources with the best available terms.
35. QUESTION -- What about the FEMA bridge program…. What’s that about? In
September of 2009, the RIIA board agreed to apply for FEMA (Federal
Emergency Management Act) status in order to be eligible for disaster
funds from a catastrophic event (such as an earthquake). FEMA funds are
only available to “preapproved” plans. An Island FEMA Committee was
formed to attend monthly meetings sponsored by Pierce County (PC) and in
April of 2010, PC will submit our application to FEMA on RIIA’s behalf.
There are no fees or obligations associated with this program. In
addition to federal funds to replace the bridge after a catastrophic
event, a “Seismic Mitigation Plan” gives RIIA
the ability to apply for additional federal grant funds in the future.
This is not an answer to the bridge issue but does give the Island
another layer of “insurance”.
36. QUESTION -- Do we need to insure the bridge? Liability and
catastrophic insurance protection is in the best interest of the RIIA
membership. Currently, the bridge is insured for $3M. Annual inspections
and repairs are required in order to keep the policy active.
Approximately 31% percent of your annual dues go to insure the bridge
(total: $28,000 annually).
37. QUESTION -- WHEN WILL THE GENERAL MEMBERSHIP GET TO VOTE ON THE BRIDGE? The
Bridge Committee is finalizing a scope of work to solicit competitive
input from engineers for more detailed information on the designs and
costs for two of the options (REPAIR and RECONSTRUCTION). Results will
be presented during a special meeting expected this fall. Since the RID
is a funding mechanism, it will require a vote to fund the “Special
Benefits Study” (SBS - see Question #8 and #9). Note: This approach
assumes that the general membership will be in favor of funding a new
bridge through a 20-year tax. Prior to funding the SBS or any of the
options, a general membership vote by mailed ballot will be required.
The decision will be determined by majority vote (two-thirds of RIIA’s
eligible voting members).
Next Steps… Results from the recent RIIA Survey provided a list of volunteer Bridge Committee Members. A Bridge Committee Meeting will be posted and those that so graciously signed up, will be notified. Thank you!
|
|
|